How to Display Week Numbers

Lee MallekMember for 21 years 5 months
Created
4
3
0

Does anyone know how to display week numbers for the duration of a project along the timescale in Powerproject?

The drop down menu does not give it as an option?

4 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Lee Right click the date

    Hi Lee

    Right click the date zone - click Insert Line - select Elapsed Units

    Move the line up or down to the required postion.

    Best regards

    Mike Testro

  2. 0
    Chris Rymer ·

    Lee Mike is correct about the

    Lee

    Mike is correct about the elapsed unit but if you need to change the week 1 position, right click in the date zone and go to Properties. Go to the Date/Scale tab and change the date zero date to where you want week 1 to start from.

     

    Chris 

  3. 0
    Lee Mallek ·

    Many thanks for your

    Many thanks for your replys.

    It seems to show Week No. 1 as -1? and if you change it to the week before the print preview shows starting on Week No.2?

    Has anyone encountered this?

  4. 0
    Mike Testro ·

    Hi Lee Read what Chris told

    Hi Lee

    Read what Chris told you and set the start date to zero at week 1.

    It also helps if you set the same start date in File > properties.

    Best regards

    Mike T.