Non-working weekend display

Laurie WillisMember for 20 years
Created
8
3
0
Hi,

I’m currently trying out Powerproject 9 and have come across a bug which seems to sill exist. Now, I’m wondering if it is a bug at all and whether there is something I am doing wrong.

The calendar we use does not include weekends, so we create a simple Calendar using the Calendar Wizard and choose to leave the weekend check boxes blank in the Wizard. We then set that Calendar as the default Calendar for new tasks.

On the bar chart, we DO want to show the weekend and it be highlighted as non-working time. To display this, we go to Format, Date Zone and, with the default Calendar set as the folding Calendar, uncheck Weekend. And here is the problem.

The display on the bar chart now goes really wide, much wider than for working days! It looks horrible. Is this a bug or something that can be fixed?

Thanks, Laurie

8 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    Laurie,
    I guess your problem is that folding calendars in Date Zone are used to display a specific time period in a specific scale.
    Try as follows (I am working with PP8 French):
    1. In the Library, create a new calendar opened 7 day a week (do not change the "working hours", as it would disable the "Next" button
    2. Assign this calendar to the Date Zone, set the bottom row as "Day" in the General tab (1st one on the left); in the 2nd tab, set the 1st day of the week Monday and the last of the week Sunday
    3. Click Close, and stretch the Date Zone on the screen until you see the 7 days of the week.
    All the best,
    Alexandre
  2. 0
    Laurie Willis ·
    Hi Alexandre,

    Thanks for your reply. However, I’m not sure I understand the 2nd step! Is this after I have created the Calendar? Which dialog box do I set this in?

    Thanks, Laurie
  3. 0
    Alexandre Faulx-Briole ·
    Laurie,
    (remember I use PP8 in French),
    1. right-click the Date Zone and open the Properties diallog box
    2. Select the new calendar in the drop-down list,
    3. In the Type box, set up the lowest level as "Day"
    4. In Day/Scale (2nd tab from left), set the week start as Monday and the week finish as Sunday, then close the dialog box
    5. Move the mouse over the Date Zone and stretch until you can see the 7 days of the week.
    If necessary, send a PM with your mail address, I’ll answer with a copy of my file.
    Alexandre
  4. 0
    Laurie Willis ·
    Hi again,

    OK, I’ve followed you this time. The days are same widths apart, but now tasks are scheduled to be worked on over the weekend, which should not be the case.
  5. 0
    Alexandre Faulx-Briole ·
    Laurie,
    No! Check that the tasks are being assigned a 5 day a week calendar: right-click on the bar, open Properties, display Task, make sure Calendar is properly set.
    In my project, I have a 15 day task starting Feb 01, 2006 and ending Feb 21; it makes well 15 days.
    To mark week-ends on the bar chart, right-click on a empty space in the bar chart, open Properties, display Non Work, check Week-end in the Categories, check what you want in "Draw ..." (2nd frame on the left).
    Alexandre
  6. 0
    Laurie Willis ·
    Alexandre,

    Thanks so much that works! Use a folding calendar for the view and a different calendar for applying to tasks. You cannot believe how long that has stumped me for!

    Laurie
  7. 0
    Alexandre Faulx-Briole ·
    Laurie,
    if you need a training on PP8 / PP9, just ask; I am only one Eurostar away from London.
    Alexandre
  8. 0
    David Bordoli ·
    Alternatively Laurie you could go to one of the Powerproject User Group meetings. The new season is about to start, they are free if you are a registered user, and there is awlays a chance to ask expert users (uncluding Asta representatives) the answer to all those niggling problems.

    (sorry A F-B, don’t mean to do you out of any business!)