comparing Percent complete and Planned percent complete
In the Open Standard
Laurie WillisMember for 20 years
- Created
- 3
- 4
0
Hi,
In my project I enter the progress of tasks using the Percent complete column. Next this I have Planned percent complete showing how much I planned to do by the current date.
What column should I use to show the difference or variance between these values?
I have tried using the Planned Percent complete variance column, but it doesn’t work as I think that it wants to compare values to a baseline, which I do not want to use.
Thanks, Laurie
In my project I enter the progress of tasks using the Percent complete column. Next this I have Planned percent complete showing how much I planned to do by the current date.
What column should I use to show the difference or variance between these values?
I have tried using the Planned Percent complete variance column, but it doesn’t work as I think that it wants to compare values to a baseline, which I do not want to use.
Thanks, Laurie
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?