Planned Percent Complete
In the Open Standard
Laurie WillisMember for 20 years
- Created
- 1
- 1
0
Hi
I’m back on one of my favourite topics again - the Planned Percent Complete complete. I’d thought I’d got my head round how it works, but it appears not!
Currently, I show Percent Complete next to Planned Percent Complete. I enter progress into the Percent Complete column and expect the Planned Percent Complete column to show what I should have done on today’s date. Instead the Planned Percent Complete is working to my Progress Period. How do I set the column to work to today’s date instead?
Thanks, Laurie
I’m back on one of my favourite topics again - the Planned Percent Complete complete. I’d thought I’d got my head round how it works, but it appears not!
Currently, I show Percent Complete next to Planned Percent Complete. I enter progress into the Percent Complete column and expect the Planned Percent Complete column to show what I should have done on today’s date. Instead the Planned Percent Complete is working to my Progress Period. How do I set the column to work to today’s date instead?
Thanks, Laurie
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?