Help on drawing bars

Christine PMember for 17 years 5 months
Created
2
1
0
Please can someone help?

I am having trouble trying to draw bars the length I want them. I have a worksheet set up with the following in the date zone area Month, Day (1-31) and Time (Hours mins).

I am trying to make a bar go from 11:00 - 13:30 but will only let me do it either 11:00-13:00 or 11:00-14:00, it wont let me do it half way.

How do i draw a bar with half hours on them please?

2 replies

Oldest first
  1. 0
    Paul Harris ·
    You need to change your snap Options. Do a search in help for snap and it will tell you all about it.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
    www.eh.com.au
    www.primavera.com.au
  2. 0
    Mike Testro ·
    Hi Christina

    As Paul wrote you do need to set the programme time units to minutes to get the results that you require - there is usually a drop down menu on the "Standard" icon menu.

    Also make sure that the work pattern in your callendar does not have any Non-Work periods in the time zone that you are looking at.

    Finally make sure that any resources attached to the task have the same calendar - this can be done in the modelling dialogue by ticking the "Calendar as Task" box.

    There will be a full description of how to apply these items in the Help directory.

    Best regards

    Mike Testro

Log in or join to reply