Help on drawing bars
In the Open Standard
Christine PMember for 17 years 5 months
- Created
- 2
- 1
0
Please can someone help?
I am having trouble trying to draw bars the length I want them. I have a worksheet set up with the following in the date zone area Month, Day (1-31) and Time (Hours mins).
I am trying to make a bar go from 11:00 - 13:30 but will only let me do it either 11:00-13:00 or 11:00-14:00, it wont let me do it half way.
How do i draw a bar with half hours on them please?
I am having trouble trying to draw bars the length I want them. I have a worksheet set up with the following in the date zone area Month, Day (1-31) and Time (Hours mins).
I am trying to make a bar go from 11:00 - 13:30 but will only let me do it either 11:00-13:00 or 11:00-14:00, it wont let me do it half way.
How do i draw a bar with half hours on them please?
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?