Skip to content

Planned Percent Complete on WBS Summary Bars

Ben JewellMember for 21 years 5 months
Created
3
4
0

Hi,

I am trying to find a way to display planned percent complete on WBS summary bars but cannot get it so show.

The 'Percent Complete' is being calculated and shown and although all the tasks within my programme are showing their individual 'Planned Percent Complete' (where applicable) there is nothing shown in the WBS summary tasks.

I have messed around with the settings for the data being used (live, current baseline etc. etc.) and I have made a copy of the current programme and used it as a dummy baseline to see if that would work but I am getting nothing....

Does anyone know if the information can be shown or am I fighting a losing battle?

I'm using version 11.0.03 (Build 063) if that is of any help.

Thanks,

Ben

3 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Ben When you say WBS

    Hi Ben

    When you say WBS Summary Bars do you mean the summaries that were created to cover a series of tasks?

    Or do you mean something else entirely?

    Progress percentages are rolled up through the summary bars automatically - in fact you can't turn them off.

    For the Planned Percent to operate you need to create a "baseline" of your project using the Baseline Manager and then select that in the Data drop down.

    Asta PowerProject is nothing like P6 because a WBS system is optional - I prefer not to bother with it.

    Best regards

    Mike Testro

  2. 0
    Ben Jewell ·

    Hi Mike, Thanks for the

    Hi Mike,

    Thanks for the reply.  I'll try and clarify what I have.

    Firstly, yes, by WBS Summary Bars I mean the summaries that were created to cover the activities within a particular WBS group. 

    I have created a WBS (I've recently come from P6 to Asta PowerProject for my current job so I find it easier to work with) and have applied a sort to the programme to show activities grouped by WBS then Date.  In the appearance settings (in the sort properties) I have selected "Summary task with all columns" for the Sub-heading, "Display banding in the spreadsheet" and "Use hierachy appearance".

    I have made a copy of the programme as it is, renamed it, imported and assigned it as the current baseline in the baseline manager but still not getting any details in the Summary Bars.  I have been through all of the available options (and combinations of options) for the Table Definition Properties for planned percent complete but have had no joy.

    The above settings have given me the view that I want and all data seems to be being displayed correctly in the WBS Heading/Summary except for the planned percent complete.

    I'm considering removing the WBS and using summarised activities but it's a hard habit to get out of after all this time!

    Regards,

    Ben

  3. 0
    Mike Testro ·

    Hi Ben For the planned data

    Hi Ben

    For the planned data to appear in the column you have to create a Baseline Programme using the Baseline Manager.

    Under the File Drop Down menu

    This creates a shadow of your working programme before any updates but is linked to your live tasks.

    Just copying the programme will not work.

    Having come from a P6 environment I understand your prediliction for WBS layers.

    You will get a better programme from Powerproject if you can forget all that and just concentrate on grouping tasks into respective programme levels.

    Please visit

    www.planningacademy.org

    where you will find interactive training manuals in the use and operation of Powerproject software.

    Best regards

    Mike Testro

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?