Hi Richard,
Is it possible to compare two taskcodes from two different librairies? The two librairies are identical. Librairy A represents the actual status and librairy B represents the wanted status at the last day of the year. When the codes are the same a priority is low, otherwise high. Is it possible to make a formula in PP to avoid exporting my report to Excel?
This formula does work but does not give the expected result;
if(TaskCodeLibrary(1174, 0, na) = TaskCodeLibrary(1223, 0, na), low, high)
Probably the result of expression TaskCodeLibrary(1174, 0, na) is not the represented name (na?) in a column.
1174 is the id of the Library. What is the meaning of the number "0" and "na" and what are the possible values? What is the result of this code?
Regards
Jan Berg