Changing the default calendar does not work

Laurie WillisMember for 20 years
Created
2
3
0

Hi

I have created a template which includes 2 calendars, a 5 day work week calendar and a 7 day work week calendar. The 5 day is the default, but when I make the 7 day calendar the default, future tasks entered do not use the 7 day one as the default, instead continuing to use the 5 day calendar.

The calendars were created using the wizard. I have tried copying the calendars into a project based on the blank template and they don't work as expected there. I have copied calendars from the Construction template to my template and they DO work as expected, so there is definitely something wrong with the calendars.

I would attached the template but I can't see this as being possible in this forum.

Any sugggestions!?

Thanks, Laurie

2 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Laurie What user level are

    Hi Laurie

    What user level are you on?

    Check that you are not still on Beginner.

    Go to Help > User Level > tick Advanced.

    This opens up all the functions in the software.

    If that is not it then you have flawed software - so go to the Asta support team and they will fix it.

    Best regards

    Mike Testro

  2. 0
    Laurie Willis ·

    HiApologies for not

    Hi

    Apologies for not responding before.

    Mike - am using Advanced Level anyway.

    Richard - that has fixed it, brilliant, thanks so much. What a strange setting. It does beg the question, why would you ever want to take property information like this based on surrounding tasks, effectively making this a random choice. I mean, what determines whether information is taken from nearby tasks or not. And why would this be set as a default (as it is with the Blank template)? Very dangerous and confusing.

    Anyway, thanks again for helping!

     

     