Import of .xer created in Asta into P6 v6.2: known problems?
In the Open Standard
Emmanuelle PrefolMember for 14 years 10 months
- Created
- 1
- 4
0
Hi,
Imported .xer file created in Asta Power into P6 v6.2, this changed some of the activities dates. As an example:
Site Attendances dates are Start 23/04/12 End 06/12/12 on the Asta .pdf received while the .xer is imported to P6 the dates are start 1/10/08 End 4/6/09.
How is this, something to do with calendars?
Also, is there in Asta the equivalent of P6 data date to whcih the progress should be scheduled to? All Asta programme updates received have a data date of 24/03/12 while some activities are complete with an end date post data date.
Thanks.
1 reply