Duration automatically changing from 1d to 6000w

Stephen WearenMember for 10 years 5 months
Created
2
3
0
Hi, trying to do a college assignment and mid way through programme, when I enter 1d for a duration it jumps to 6000w. Has anybody had a similar issue or know what setting will rectify this. Thanks

2 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Stephen - welcome to

    Hi Stephen - welcome to planning planet

    Never heard of that one before - have you created a buffer task by accident - if so change it back to a normal task.

    Next check your calendars both on the task and any resources.

    Can you change it back to 1d by either:

    Change the dates in the spreadsheet?

    Drag the task back with the mouse?

    You could have a glitch on the software - try deleting the task and putting it on a new row.

    If nothing else then contact Asta Support - I presume you have an up to date licence.

  2. 0
    Ameya Talekar ·

    Hi, Check if you have

    Hi, 

    Check if you have resources in the particular activites and been closed on single day span (Act Start-Finish) it accumulates your planned resource distributio and distort the complete timeline. I just am putting my guess as it occers here in my Schedule several times when we close DELETED Provisional sums acitviities with cost loaded into it.

     

    Regards,

    Ameya