Using Formula answer in another Formula

Chris LothianMember for 19 years 5 months
Created
2
4
0

Hi all,

Does anyone know how to / if you can refer to an answer of a formula in part of another formula?

If you can, could you please explain how?

Kind Regards,

 

Chris

2 replies

Oldest first
  1. 0
    Chris Ray ·

    Hi Chris,if your not able to

    Hi Chris,

    if your not able to refer to other formulas, you will need to add the existing formula into the new formula e.g

    formula 1 - display long for all task over 10 days and short for less than 10 days

     

    if(duration > '10d', "Long","Short")

    formula 2 - depending on the result of Long or Short display different messages

    if(if(duration > '10d', "Long","Short")="Long","Task over 10 days","Task less than 10 days")

     

    I would always recommend that when building a new formula, build it in small sections so you know that each part works.

  2. 0
    Chris Lothian ·

    Thanks Chris.Keeping them

    Thanks Chris.

    Keeping them simple, and a lot of trial and error is the only way i can get a formula to work, so was hoping to avoid creating complex Formulae. If you're able to help, i've posted again with the details of the specific formula:

    http://www.planningplanet.com/forums/asta-powerproject/537833/formula-duration-between-tasks-based-code-library-allocation

    Thanks,

    Chris