Calendar - 7 Day Working Week

Dominic PlannerMember for 9 years 4 months
Created
1
3
0

I am creating a programme to completion that will require weekend working. 

I have set the calendar to 7 day working week but when I set an activity to work saturday and sunday, the activity bar jumps to the monday. 

How do I prevent this from happening?

Thanks 

1 reply

Oldest first
  1. 0
    Mike Testro ·

    Hi DominicAre you sure that

    Hi Dominic

    Are you sure that you have set the calendar to 7 working days?

    Also check that the calendar on your resource allocation is the same - it will over ride the plan calendar.

    For instance if you have a gang of 3 carpenters - catholic - jewish and muslim - each with their own calendar you will only get 4 days work in the eek.

    Best regards

    Mike Testro