Week numbers in the date zone

Alex HoughMember for 9 years 6 months
Created
2
3
0

Hi all

I have a 30 week programme that has a 2 week shutdown over Christmas. The current week numbers in the date zone show it coming out as 32 weeks, is there any way to not show week numbers over the 2 week shutdown?

ie. up to week 5, then nothing for 2 weeks, then in January start from week 6?

Thanks in advance!

Alex

2 replies

Oldest first
  1. 0
    Ben Taunt ·

    Hi Alex,In the Date Zone

    Hi Alex,

    In the Date Zone Properties (right-click within the Date Zone > Properties), the line currently representing your week numbering will likely state Type = "Elapsed Units", Time Unit = "Weeks".  If you change Elapsed Units to instead be "Working Units", it will reflect your folding calendar's exceptions.  You should then see the change you want in your date zone.

    Best wishes,

     

    Ben @ Powerproject

     

     

  2. 0
    Alex Hough ·

    Brilliant, that worked thanks

    Brilliant, that worked thanks Ben!