Week numbers in the date zone
In the Open Standard
Alex HoughMember for 9 years 6 months
- Created
- 2
- 3
0
Hi all
I have a 30 week programme that has a 2 week shutdown over Christmas. The current week numbers in the date zone show it coming out as 32 weeks, is there any way to not show week numbers over the 2 week shutdown?
ie. up to week 5, then nothing for 2 weeks, then in January start from week 6?
Thanks in advance!
Alex
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?