Collapse completed summary tasks only

Dariusz CMember for 7 years 10 months
Created
2
4
0

Hi 

 

Is there any way to collapse summary tasks where OPC = 100% only?

My schedule contains a lot completed summary tasks so I don't want to show them in the view with entire content.
I can do this manually but looking for more convienient way.
Summary Tasks where OPC is under 100% should not be touched and be visible with all tasks underneath.
Something like below:


Thanks in advance!

2 replies

Oldest first
  1. 0
    Mike Testro ·

    Sorry DariuszYou have to do

    Sorry Dariusz

    You have to do it manually.

    One Click and save is all you need.

    You don't have to show all your sub tasks.

    You can have a sub summary labelledd 100% and move every complted task down into that showing only the work in prgress.

    Best regards

    Mike T.

  2. 0
    Konstantinos Parsalidis ·

    Dariusz,You can if you make a

    Dariusz,

    You can if you make a small compromise and that is not showing the completed tasks under an incomplete summary.

    The filter would be 

    Criteria 1 - Summary Tasks with Task Progress Completed

    Criteria 2 - Tasks or Milestones or Summary Tasks with Task Progress Specific Progress Amount Less Than 100%

    Also, Objects must meet ANY criteria

    Otherwise, I'm sure you could write an SQL statement but not sure I can help you with that.

    Let me know if that works for you.

    Kind regards,

    Konstantinos

Log in or join to reply