Using Task Work Feature
In the Open Standard
Prince Jhegro PeregrinMember for 6 years 7 months
- Created
- 4
- 5
0
Greetings everyone,
May i ask your expertice about AstaPP?
WH is 8:00am - 5:00pm, Building Construction, Creation of BL Sched.
I want to use the Task Work feature in AstaPP, while doing it, i noticed that it makes my activies to finish in-between the day which allows the successor to start on the same day. I want the successor to start the next day even if the predeccessor is already finished before the end of the working hours.
May I ask someones assistance on this.
Thank you very much in advance.
Prince
4 replies