Planned % not matching with Actual

Mohamed AbraarMember for 9 years 7 months
Created
1
5
0

please help, planned % not matching with actual % , i dont know how.\

1 reply

Oldest first
  1. 0
    Jerome Odeh ·

    Your screenshot shows the

    Your screenshot shows the Planned % & Actual % do match where the start & finish dates are the same.

    If you are worried that Planned % comes with decimals while Actual % doesn't, it's because the Planned % is calculated using Custom Field formula while Actaul % is a default Microsoft Project field.

    This blog post might help you. Microsoft Project Baseline Percent (%) with Weighted Summary Roll-up