Custom Baseline
In the Open Standard
Will RussellMember for 23 years 6 months
- Created
- 0
- 4
0
I am having a problem with saving baselines, Baseline 10 in this case.
I have a material resource of a certain value and I want to update the value of this resource, in Baseline10 cost, because its original value was typed in wrong.
The assignments associated with this resource reflected the correct amount but did not “rollup” to reflect the total - no problem I thought and I input the summed value into the resource Baseline10 Cost field and saved the file safe in the knowledge of a job well done.
I came to open it the next day and it had reverted to the previous value.
I thought that possibly I should have put the correct value against the resource in the Resource Sheet so I tried this but again after saving, closing and reopening the file it had reverted to the previous value again.
The crux of the matter is that in the other views I use, Task Usage and the Gantt view, the baseline values rollup, the assignments in the Resource Usage View against this item reflect the correct amount but the total remains incorrect.
Has anyone come across this problem? Was there a way around it? Is there a setting which I have not come across which will automatically rollup the assignment values in the Resource Usage View?
Any information regarding this would be greatly appreciated.
Will
I have a material resource of a certain value and I want to update the value of this resource, in Baseline10 cost, because its original value was typed in wrong.
The assignments associated with this resource reflected the correct amount but did not “rollup” to reflect the total - no problem I thought and I input the summed value into the resource Baseline10 Cost field and saved the file safe in the knowledge of a job well done.
I came to open it the next day and it had reverted to the previous value.
I thought that possibly I should have put the correct value against the resource in the Resource Sheet so I tried this but again after saving, closing and reopening the file it had reverted to the previous value again.
The crux of the matter is that in the other views I use, Task Usage and the Gantt view, the baseline values rollup, the assignments in the Resource Usage View against this item reflect the correct amount but the total remains incorrect.
Has anyone come across this problem? Was there a way around it? Is there a setting which I have not come across which will automatically rollup the assignment values in the Resource Usage View?
Any information regarding this would be greatly appreciated.
Will
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?