Resource Expenses

Forum GuestMember for 17 years 8 months
Created
2
3
0
All

Using Project 2003. I have to enter a standard resource cost and then apply a daily per diem cost on top of that for a period of time. Eg:

1-31 Jan - £300/day
1-29 Feb - £300/day + £28/day
1-31 Mar - £300/day

I have to differentiate this £28/day cost as an unbillable expense but still need to be recognised as part of the project cost.

What is the easiest way to do this?

Thanks in advance

Dan

2 replies

Oldest first
  1. 0
    Will Russell ·
    Using the Cost tab in the Resource Information box you can put in specific costs for certain periods of time as you wanted.

    Will
  2. 0
    Forum Guest ·
    Thanks

    I’ve had a play around with it and as a workaround have added it as a material cost and loaded the number of units in the resource allocation to equal the number of days that task requires.

    If anyone can think of a smarter way of doing it, please let me know.

    Dan