Actual Work

Forum GuestMember for 17 years 8 months
Created
1
3
0
Is there any way of LOCKING the actual work field. Whenever I explore changes in resources, time, duration - my (past)actual work figures alter.

1 reply

Oldest first
  1. 0
    David Barry ·
    Make sure "effort driven scheduling" is not operational.

Log in or join to reply