Problems while updating the actual work hours
In the Open Standard
Forum GuestMember for 17 years 8 months
- Created
- 4
- 4
0
When I update the actual hours for completed task, the actual finish date does not get updated. when I manually type in the actual finish date, the % complete changes to 100%, duration gets automatically calculated(which is totally wrong), actual hours changes and it is equal to work and rem work is 0hrs.
Note: Effort Driven is unchecked.
When I have Effort Driven checked, I dont face the above problem but when I enter the actual hours, it modifies the actual start and actual finish dates.
How do I handle this problem??? Any help is appreciated.
Thanks
Note: Effort Driven is unchecked.
When I have Effort Driven checked, I dont face the above problem but when I enter the actual hours, it modifies the actual start and actual finish dates.
How do I handle this problem??? Any help is appreciated.
Thanks
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?