Big projects
In the Open Standard
OS
Oleg SMember for 21 years 10 months
- Created
- 14
- 5
14 replies
Oldest first- 0PJPhilip Jonker ·Hi Oleg,
If you are using MSP have a look at MS Project specifications in the help file. The no of activities is limited according to the memory available. The exact number for the amount of memory available is not spefified. However, I suggest you try MS Project help desk, to find out the exact amount. I hope this helps.
Regards,
Philip Jonker
- 0JSJaco Stadler ·I remeber running about 5 Years ago in MS a project with 1200 activity’s with resources etc. I have found that when I calculate I had to go for a 20 Minute Walk then come back and then I might have some answers. I know time’s has changed but this memory will always be with me when I think MS Projects.
- 0PJPhilip Jonker ·Hi Jaco,
I was on a project in 1991-4, where we ended up with a project with 35 000 activities in the end, we were using Open Plan V4 dos at the time, and hit a limit when we went past 15 000 activities, and then found out we needed an extended scheduler attachment which allowed us to go up to 40 000 acts. The problem then came in the sense that we had to wait about 16 minutes, for the program to schedule, then somebody decided that we needed resource levelling:-) This process took an hour and forty minutes. Fortunately everything has sped up so much today, that the same process would take about 8mins, time enough for a cup of coffee:-) As for MSP, no comments! The feeling is mutual.
Regards
Philip Jonker
- 0PJPhilip Jonker ·Hi Vladimir,
What I was saying, it used to take an hour and 40 mins in open plan in 1993, based on my experience in the last project where I had 9000 activities using P3, I could run a resource scheduling in just under three minutes, so I assume it would take approx 8 min to schedule 35 000 acts. This is of course dependant on the computing speed etc, you have available. The actual point was about the limitations of planning software.
Regards
Philip - 0VLVladimir Liberzon ·Thank you for reply.
Unfortunately the dependency is not linear especially with resource leveling. If you will copy and paste your project 3 times you will find that the time of resource leveling is much longer than 8 minutes. And you will wait for quite a long time waiting for the paste operation to be completed.
Best Regards,
Vladimir - 0PJPhilip Jonker ·Hi Vladimir,
I think the problem with copy paste/scheduling time can be resolved by increasing your memory (RAM) as this is a problem in databases, and not a calculation problem. A lot of database handbooks point out this problem, a further improvement can be gotten by using a faster hard drive, as much of the time spent in the scheduling process is taken up by information being written to the drive. On the project with 9000 acts I got to a stage where I had increase my computor’s memory to run certain reports, and the result was faster resource levelling and scheduling as an added bonus. The speed of copy/paste operations, which I used to update, certain of-site activities, had also sped up.
Regards
Philip
- 0VLVladimir Liberzon ·Hi Philip,
I tried copy/paste on the computer with 2 Gb of memory. If it is not enough then the program is too demanding. I know that it is a problem of the standard databases. That is why Spider Project uses its own specially developed database that is much faster. But what I wrote about the speed of leveling is also true. Just try to do what I suggested and you will see that the time of leveling will be much more than you expected.
Best Regards,
Vladimir - 0PJPhilip Jonker ·Hi Vladimir,
Unfortunately I do not have a copy of the 9 000 act program with me, as I am away from home, and further I have no experience of Spider either. However, I have extensive experience with databases. An interesting fact was that during the time we were running the 35 000 act project ie 1990-4, we were running foxbase with open plan v4 for dos, in that time foxpro was released. We switched to foxpro towards the end of the project, and this step reduced res levelling times to about a third.
As a matter of interest what is the size of your project? When I have a chance I will look up spider on the net, and find out more.
Regards
Philip
- 0VLVladimir Liberzon ·Hi Philip,
I am working in consulting and am involved in management of projects of different size. These projects include oil and gas (Caspian Pipeline construction as an example), telecommunications, construction, ship building, software development, etc. The size of CPC project - more than 9000 activities, 1145 resource types. The size of ship building multiproject (several ships) - 92000 activities. Recently we scheduled 270000 activity project for one of our customers who wanted to see if it is possible (leveling took 4 minutes 39 seconds). The speed of leveling depends very much on the complexity of resource assignments - skill scheduling, financial and supply leveling make it slower, though reasonable.
Usually project size is between 3000 and 20000 activities. Multiproject (portfolio) size is much larger.
If you asked about the size of Spider Project Demo for download - it is not large, less than 6 Mb.
Regards,
Vladimir