Calendars

Gerry MorganMember for 21 years 10 months
Created
4
4
0
I have 4 calendars set up in my project plan, if I go to reports I can print out the detail of the Base calendar in list form showing working and non working days that I have set up, does anyone know how or even if I can print out the details of the other calendars in the same list format.
GM

4 replies

Oldest first
  1. 0
    Paul Harris ·
    Double click anywhere in the calendar to open the Calendar form, select the required calendar from the Date Shading form.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Book Publishers, Training & Consulting
    www.eh.com.au
  2. 0
    Gerry Morgan ·
    Thanks Paul, I’ll give it a try
    GM
  3. 0
    Alexandre Faulx-Briole ·
    Do you want to print a report showing "Base" calendars or Resource calendars?
    MSP cannot print resource calendars; to print a report about "Base" calendars, simply go to View, Reports, Overview, Working Days: MSP 2002 (for instance) shows every base calendar ona separate page.
    All the best
  4. 0
    Gerry Morgan ·
    Hi Alexandre

    Thanks for the reply, it was the resource calendars I was trying to print out in list form but as you say I don’t think that is possible.

    Thanks again. GM

Log in or join to reply