Elapsed Time Shown on Timescale
In the Open Standard
Tony McClennonMember for 23 years 10 months
- Created
- 9
- 4
0
Hi,
I am trying to get the MS Project timescale to show the time elapsed, but instead of it being from the start or finish (as per the options in the Timescale menu), I need to show it from a particular milestone/date within the project.
Some tasks have been completed or or in progress, but the end-user needs to see the time elapsed from this critical milestone point.
Can anyone advise as to how this may be achieved?
TIA.
I am trying to get the MS Project timescale to show the time elapsed, but instead of it being from the start or finish (as per the options in the Timescale menu), I need to show it from a particular milestone/date within the project.
Some tasks have been completed or or in progress, but the end-user needs to see the time elapsed from this critical milestone point.
Can anyone advise as to how this may be achieved?
TIA.
9 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?