Stretching Activity durations
In the Open Standard
Alex CostarasMember for 21 years 4 months
- Created
- 7
- 5
0
Is there a way of stretching an activity’s duration in MSP. I’ve got a test activity that I want to span the gap between the earliest and latest equipment deliveries, but not as a hammock.
e.g.
......|Act A ======|
........................|Act B ==========|
Act C ===========================
What I need is for the duration of Act C to fluctuate as the predecessors change. But I want it to be a Task, not a summary bar or hammock
e.g.
......|Act A ======|
........................|Act B ==========|
Act C ===========================
What I need is for the duration of Act C to fluctuate as the predecessors change. But I want it to be a Task, not a summary bar or hammock
7 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?