MSP Forcing an activity to start on a new day/whole day
In the Open Standard
John MatthewsMember for 19 years 7 months
- Created
- 12
- 5
0
Although I have seen solutions to similar problems on the web, I have been unable to find one that solves my problem so am hoping someone can help.
I have a task that starts on a Monday and takes 0.2 duration of a day. It has a successor task which takes 2 day duration. This successor task needs to happen all on 2 full days not partial ones.
Left to its own devices MSP will start the successor task part way through Monday with the task finishing part way through Wedensday. Is there a way to force the successor task to not start part way through a working day, but in the example above start on the Tuesday & finish on Wednesday? Some kind of force start to new day ability!
Thanks in advance for any suggestions.
I have a task that starts on a Monday and takes 0.2 duration of a day. It has a successor task which takes 2 day duration. This successor task needs to happen all on 2 full days not partial ones.
Left to its own devices MSP will start the successor task part way through Monday with the task finishing part way through Wedensday. Is there a way to force the successor task to not start part way through a working day, but in the example above start on the Tuesday & finish on Wednesday? Some kind of force start to new day ability!
Thanks in advance for any suggestions.
12 replies
Oldest firstLog in or join to reply