BCWS at Task Level not calculating
In the Open Standard
Colleen CoyneMember for 21 years 4 months
- Created
- 2
- 8
0
I’ve seen the threads and postings regarding BCWS not calculating at the summary level but my Project (2000 SR-1) randomly does not calculate BCWS data at the task level.
The majority of the tasks have BCWS calculations but many do not and as a result my overall BCWS is always zero...
I’ve tried rebaselining but it doesn’t seem to help at the task level.
Anyone know a workaround?
Thanks!
The majority of the tasks have BCWS calculations but many do not and as a result my overall BCWS is always zero...
I’ve tried rebaselining but it doesn’t seem to help at the task level.
Anyone know a workaround?
Thanks!
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?