BCWS at Task Level not calculating

Colleen CoyneMember for 21 years 4 months
Created
2
8
0
I’ve seen the threads and postings regarding BCWS not calculating at the summary level but my Project (2000 SR-1) randomly does not calculate BCWS data at the task level.

The majority of the tasks have BCWS calculations but many do not and as a result my overall BCWS is always zero...

I’ve tried rebaselining but it doesn’t seem to help at the task level.

Anyone know a workaround?

Thanks!

2 replies

Oldest first
  1. 0
    Tom Hadley ·
    Work around

    Buy a program that works properly, get yourself trained in Earned Value not just how to use MSProject

    Distrust absolutely any cost calculations done by MSProject

    I will train you just email me PMwork1@bigpond.net.au

    Regards

    tom
  2. 0
    James Griffiths ·
    Colleen,

    Have set the status-date, via Project>Project Information?

    James.

Log in or join to reply