Unlink Remaining Duration & % Complete
In the Open Standard
Ian ThomsonMember for 23 years
- Created
- 3
- 5
0
I have an issue in MS Project where I would like to unlink remaining duration from % complete. It was a function I used quite often in P3 but I cannot find it in MS Project. It is a real issue on construction projects. Any wise men out there who can help? Thanks in advance.
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?