Unlink Remaining Duration & % Complete

Ian ThomsonMember for 23 years
Created
3
5
0
I have an issue in MS Project where I would like to unlink remaining duration from % complete. It was a function I used quite often in P3 but I cannot find it in MS Project. It is a real issue on construction projects. Any wise men out there who can help? Thanks in advance.

3 replies

Oldest first
  1. 0
    Jihad Daniel ·
    Use the Autocost Rules and untick the remaining duration & % complete.
  2. 0
    Philip Jonker ·
    Hi there, the autocost thing is in P3. Busy loading MSP at the moment, if I can find something, will reply. Wher are the MSP Fundi’s?
  3. 0
    Jaco Stadler ·
    Hi Ian

    The Problem with MS is

    % Complete = % Time Complete
    You Can use % Work Complete
    Original Duration in P3 is known as baseline Duration in MS.
    And Duration is Actual Duration & Remaining Duration

    I Hope this Helps