Can anyone advise whether or not it is possible to show the duration of the summary tasks in anything other than days?

I have been trying to set the summary bar to show the duration in weeks or months, but have failed to achieve this so far.

Over to the MSP Gurus!!!

Cheers,

Tony

3 replies

Oldest first
  1. 0
    Tony McClennon ·
    Sorry - should have mentioned that I am working with MSP2000.

    Tony
  2. 0
    Sukumaran Subaramaniyan ·
    Go to Tools > Options > Schedule and in the following field "DURATIONS IS ENTERED IN" change to either Weeks or Months.

    Regards.
  3. 0
    Tony McClennon ·
    Sukumaran - many thanks, just the thing.I must have been having one of those "forgetful" moments!!!

    Regards,

    Tony