Setting Resource Costs in Cost Tables

José ZayasMember for 21 years 1 month
Created
1
4
0
We would like to enter average costs of resources in the Enterprise Resource Global tables for the next couple of years.

I understand that MSP allows you to enter this information for each resource individually by entering the effective date and the new rate.

Is there a way to enter this for the entire resource pool to be able to generate cash flow forecasts without having to modify this for each resource or for each project?

1 reply

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    hello,
    if all or several of your resources have the same hourly / daily rate, select the resources, open the Resource information dialog and enter the data in the corresponding field(s)
    if you want to create a resource table in MS Excel or any other spreadsheet able to save xls files, you will be able to import data by using the File, Open, xls file, import map feature
    Alexandre

Log in or join to reply