Lag’s Calendar

Marcio SampaioMember for 20 years 11 months
Created
6
4
0
Hello all,

Could u please tell me which calendar do MS Project respect to calculate lags?? (predecessor, successor or another)

Thanks.

Marcio Eduardo.
Rio de Janeiro - Brazil

6 replies

Oldest first
  1. 0
    Marcio Sampaio ·
    And where can I configure this??

    Thanks
  2. 0
    Ronald Winter ·
    I have been told that MS Project lags are calculated using the Default Calendar.
  3. 0
    Marcio Sampaio ·
    Thanks Ronald.

    I’m not a MSP user ... so i dont use to read MSP threads ... thats why i didn’t know about that.

    Thanks again.

    Regards.

    Marcio Eduardo
  4. 0
    Ioannis Leontiou ·
    It uses Default Calendar, Unless yuo had configured and assign a Task Calendar for the tasks reference to
  5. 0
    Tom Boyle ·
    In MSP 2003, working days in lag relationships are computed based on the Successor Activity’s calender. This defaults to the Project Calendar if no other calendar is specified for the successor activity. (I think P3 uses the Predessesor’s calendar).

    [This is a correction I just learned today, so I thought I’d post it for the record.]
    BR, tom
  6. 0
    Paul Harris ·
    There are two other options for lags:

    Elapsed lags, say FS+10edays will give you an elapsed lag ignoring the Successor calendar.

    Percent Lags, say FS-50% which will allow the successor to start 50% through the duration of the predecessor.

    P3 and SuerTrak use the predecessor calendar but Primavera Enterprise gives several options.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers & Consulting
    www.eh.com.au

Log in or join to reply