Resource units

Vinod RaturiMember for 20 years 2 months
Created
2
2
0
hi ,

My query is suppose my project calander is 8 of hrs and my resource calander is 24 hrs. If i have to assign that resource to a task that consumes 4 hrs , what should be my assignment fig for that resource , should it be 50% or 16%.

2 replies

Oldest first
  1. 0
    Zhang Haixiang ·
    It’s a complex issue.

    In MSP there are 3 types of task, fixed duration, fixed work and fixed units. they act differently when assign/change recource.

    for your question, use 50%, but maybe the duration will change based on task type.

    Goto online help for details for task type,then try it
  2. 0
    Vinod Raturi ·
    hi Zhang ,

    I think 16% is correct . My logic being a resource is available to us as per their base calanders , so it is with respect to that time available we should fill in the assignment units.

    Any different Views ?