can any body tell me, the differences between cost driven schedules and duration driven schedules.
and also how to go about cost scheduling.... Tolu

1 reply

Oldest first
  1. 0
    Ruben Quintal ·
    hi Tolu,

    the cost driven schedule depends on the cost in computing its duration and activity sequencing,
    ei. duration(month) = activity cost/available monthly cashflow
    while duration driven schedules are more concern about the allowed duration or the required milestone or completion date.