Handling Fixed Manhours...
In the Open Standard
Nadar VinodMember for 19 years 8 months
- Created
- 4
- 6
0
Hi everybody, Nadar Vinod from India here.
I am new to this forum, and you know why I am here!! I need to understand MS projects from immediate application pointy on view.
While preparing a schedule for one of my projects in MS project, I have come across a situation where I need help from this forum...
The Situation is something like this..
I have an activity ’ABC’ that has a start date (Dec 29,2006) and an end date (March 8, 2007). Contractual Agreement is that 1 resource ( say Mr. XYZ) would be appointed for handling this activity. The contractual agreement is for 70 Manhours. How, do I implement this in MS projects.
Pardon me, if my request looks very annoying, but I am a begineer.
I am new to this forum, and you know why I am here!! I need to understand MS projects from immediate application pointy on view.
While preparing a schedule for one of my projects in MS project, I have come across a situation where I need help from this forum...
The Situation is something like this..
I have an activity ’ABC’ that has a start date (Dec 29,2006) and an end date (March 8, 2007). Contractual Agreement is that 1 resource ( say Mr. XYZ) would be appointed for handling this activity. The contractual agreement is for 70 Manhours. How, do I implement this in MS projects.
Pardon me, if my request looks very annoying, but I am a begineer.
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?