hi ms project expert.
is there any option to assign a fixed amount of works and a duration to activities,
basically I have the amount of work for the activities from the estimation software, and I want the duration to be independant from the resource assignement is that possible in ms project ( something like fixed duration & units in P6).
regards
mimoune
ps
I am not trolling here, for some reason the client wants ms project and i have to live with it :(