Skip to content

Customised Timescale

James ArundellMember for 19 years 7 months
Created
1
3
0
Is it possible to set up a customised timescale in MS Project. I would be looking to have period for the top level (13 periods a year/ 4 weeks a period) labelled 1 - 13 then have weeks underneath at the second level labelled 1 - 4.

Thank you in advance.

James Arundell

1 reply

Oldest first
  1. 0
    James Griffiths ·
    Hi James,

    To the best of my knowledge, the answer is NO. However, if you double-click on the timescale, in the Gannt Chart, then you’ll be given the various timescale formats. Rememeber, though, MSP is a scheduling package, NOT an accounting package.

    Cheers.

    James.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?