Bar Scale
In the Open Standard
Mark ChapmanMember for 20 years 5 months
- Created
- 2
- 4
0
I am struggling with a problem. I have 3 activities consecutively with 8 hours each against them on a 24 hour calendar. The ES & EF are correct - see below
8 hrs 23/06/10 00:00 23/06/10 08:00
8 hrs 23/06/10 08:00 23/06/10 16:00
8 hrs 23/06/10 16:00 24/06/10 00:00
But the bar scale for them is completely strange. It look something like this:
-----
i
i
(Basically the bar length for the 2nd & 3rd activities is much shorter than the 1st)
If I change the FS constraints to SS then the bars are the same length.
Only when I change the timecale to 2 hour separation are the bar lengths equal!
Help - I am going mad on this one.
8 hrs 23/06/10 00:00 23/06/10 08:00
8 hrs 23/06/10 08:00 23/06/10 16:00
8 hrs 23/06/10 16:00 24/06/10 00:00
But the bar scale for them is completely strange. It look something like this:
-----
i
i
(Basically the bar length for the 2nd & 3rd activities is much shorter than the 1st)
If I change the FS constraints to SS then the bars are the same length.
Only when I change the timecale to 2 hour separation are the bar lengths equal!
Help - I am going mad on this one.
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?