Equipment usage
In the Open Standard
Jimm LitschewskiMember for 19 years 4 months
- Created
- 3
- 3
0
I am trying to put together a production schedule and the most significant limiting factor is the availability of test equipment. I have two test racks (Rack #1 and Rack #2) and at each rack can test only one unit at a time.
How can I set up my MS Project schedule such that I can assign both test stations to the testing steps and let project determine which one is available to use?
I thought I could put them in a group and let project pick from there, but I don’t know how to assign the group to the task. Also, is there another way to define test equipment as a resource instead of as a personnel type resource? I would think there is a difference but maybe there isn’t.
Let me know if you need more clarification on my issues ;)
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?