Status Date and Work Shown to be Perfromed Before

N Curgus PSPMember for 23 years 3 months
Created
2
2
0
Can someone explain how MS Project 2003 calculates the start and finish dates for the activities scheduled to start before the status date, BUT HAVE NOT STARTED. When I tested this start and finish dates would still be before the status date and the predecessor relationship WAS IGNORED. For the activities that have started when a right option is selected remaining work is shown after the status date, which was correct.

Can this be explained and is it any way that an activity has not started can be “moved” after the status date?

Thanks,

2 replies

Oldest first
  1. 0
    Andrew Owenson ·
    N

    Cannot help with the how, but if you go to Tools, Tracking, Update Project. Tick the reschedule uncompleted work, as long as your status date is correct the activities will adjust to the right of the status date - works for me

    Best Regards

    Andrew
  2. 0
    Alexandre Faulx-Briole ·
    Hello,
    go to Tools, OPtions, Calculation, use the options #2 to #5 under Calculation options for (current) project (don’t know the exact name in English as I am using the French version)
    looks like MS Project would like to simulate P3, with limited success
    Alexandre