Driving predecessor again in MSP

Nicolas IgersheimMember for 19 years 3 months
Created
6
5
0
Hi all I a giving an old problem a new try! Has any of you geeks written a VB or else routine in order to determine which is the driving predecessor of a task? I would like to show the driving predecessor on the left of each critical task’s bar. Tks in advance!

6 replies

Oldest first
  1. 0
    Paul Harris ·
    MSP 2007 does show this now, but it has a few bugs and may be best to wait for the first SP before upgrading.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers & Consulting
    www.eh.com.au
  2. 0
    Niek Zonneveld ·
    Nicolas,

    Rod Gill’s book "VBA Programming for Microsoft Office Project" ISBN: 0-9759828-7-7 contains the macro you’re looking for, including a full explanation of the code.

    Cheers,

    Niek.
  3. 0
    Nicolas Igersheim ·
    Tks a lot Niek

    Amazon.com here I come!

    I’ll let you know about the results.

    Cheers
  4. 0
    Alexandre Faulx-Briole ·
    Paul,
    where have you found that MS Project 2007 displays driving links differently from the others?
    Thanks,
    alexandre
  5. 0
    Paul Harris ·
    Alexandre

    Microsoft Project 2007 introduced a Task Drivers form that indicates which is the driving predecessor and whether the schedule has been Resource Leveled. It will also display the effects of leveling.

    Select the Task Drivers icon on the Standard Toolbar to open the Task Drivers pane

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers & Consulting
    www.eh.com.au
  6. 0
    A D ·
    Read this:- Covering everything from the basics of project management to the ins and outs of integrating Project 2007 with other Office applications, Project 2007 Essential Training is a comprehensive and valuable course. Instructor Lorna A. Daly teaches users how to work with Project 2007 to best analyze and manage business ventures of any scope. She explains how to organize resources and assign work, how to streamline processes and resolve project conflicts, and how to customize and optimize Project 2007 for future tasks. Exercise files accompany the tutorials.


    http://rapidshare.com/files/48544985/Project.2007.Essential.Training.part1.rar
    http://rapidshare.com/files/48544930/Project.2007.Essential.Training.part2.rar
    http://rapidshare.com/files/48545022/Project.2007.Essential.Training.part3.rar
    http://rapidshare.com/files/48855440/Project.2007.Essential.Training.part4.rar

    I hav not downloaded so far. But the review was good. Good Tutorials!!

    :-)