Hi All,
I am moving from P6 to MSP and am trying to get to grips with the changes in user interface.
One ommission I have noticed in MSP is the predecessor and successor GOTO button.
In P6, when the bottom layout is visible and on any of the relationships tabs, if you select an activity, the list of predecessors or successors appears, together with any relevant details like duration, float, driving etc. In this view, you have the option of clicking the GOTO button and P6 will jump to the relevant highlighted activity in this list.
In MSP, there is a similar view, in the split window, where you can view the same predecessor or successor information, within a similar list. The only thing missing is the GOTO button.
Is there any means in which you can highlight an activity in this list of predecessors or successors and make the programme jump to it.
This was the way I used to follow the logic paths through my programmes, and I can’t find this facility anywhere in MSP.
Thanks in advance,
Dean.
I am moving from P6 to MSP and am trying to get to grips with the changes in user interface.
One ommission I have noticed in MSP is the predecessor and successor GOTO button.
In P6, when the bottom layout is visible and on any of the relationships tabs, if you select an activity, the list of predecessors or successors appears, together with any relevant details like duration, float, driving etc. In this view, you have the option of clicking the GOTO button and P6 will jump to the relevant highlighted activity in this list.
In MSP, there is a similar view, in the split window, where you can view the same predecessor or successor information, within a similar list. The only thing missing is the GOTO button.
Is there any means in which you can highlight an activity in this list of predecessors or successors and make the programme jump to it.
This was the way I used to follow the logic paths through my programmes, and I can’t find this facility anywhere in MSP.
Thanks in advance,
Dean.
15 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?