Greetings Gurus,
Haing (in my opinion) beig spoilt and never having used MS Project Server 2003 in anger previously, I came across a funny little thing the other day which I’m sure will be very easily explained.

One particular resource assignment on a 48 hour actiity had a required effort of 40 hours, however the percentage was displaying 116%, which to me seemed a bit odd.

Could someone please explain.

Thanks
Andy

1 reply

Oldest first
  1. 0
    Niek Zonneveld ·
    Andrew,

    The first thing I would normally check is if the assignment work has been edited. You can do this by looking at the indicator column in the default assignment view, or by double clicking on the assignment.

    If the work contour is not flat (but contoured, for instance) the regular schedule equation (D=W/U) no longer holds.

    Hope this helps,

    Niek.