Tracking The Quantities Using MSP2003

Md Dasuki SamadMember for 18 years 11 months
Created
1
5
0
Hi,

Currently, I monitoring and scheduling highway & bridges project.
I’ve difficulties to track and find out the quantity of materials supposed to be ready at any date referred such as steel bars tonnage, m3 concrete and m3 of earthworks.
Those information are required in order for me to prepare the ’order material list’ for my project.
kindly please explain and advise me on how should i solve this matter.I also have no idea whether MSP2003 able to do this or not.
Please help.
Thank you.

1 reply

Oldest first
  1. 0
    Johny Kesserwany ·
    Hi,

    Did you assigned those quantities on related activities as resources?

    If yes you can execute a report showing the workload by time period which will be your budgeted quantities/period.

    Regards

Log in or join to reply