Tracking
- Created
- 7
- 2
Dear All,
I have created a schedule and the same has been approved by the clients. Now we want to monitor the progress based on this schedule. I have saved a copy of this original. Now the following steps were done by myself to track the progress:
Tools - Tracking - Set Baseline (Baseline 1) ,for Entire Project . OK.
Then in the Gnatt Chart I introduced two columns for the Actual Start & Actual Finish along with Start and Finish of the approved schedule dates.
Then started to update the progress by entering the Actual starts and finishes for the activities, my dates in the Start and Finish also changes.
Not able to show the clients of the present condition.
Can anybody help me.
Thanks in advance for your help.
Rohit