Need to show day and night time activities

Amit RaisinghaniMember for 18 years 6 months
Created
3
3
0
need help to show day and night time activities, and filtering the night activity schedule as well as showing the critical path.

3 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    Amit,
    Create a new "Night time" calendar, and apply to activities that occur during the night; then create a filter where calendar = "night time"
    Alexandre
  2. 0
    Amit Raisinghani ·
    Thanks Alexandre for your reply. Could u please run me through, how i should create a new calendar and filter it out please.
  3. 0
    Alexandre Faulx-Briole ·
    Amit,
    1. Calendar: Tools, Change working time, Create
    2. Apply calendar to tasks: Project, Task Information, Advanced, Calendar
    3. Filter: Project, Filtered for, More filters, New; Task calendar equals to Night Time
    Hope this helps
    Alexandre