MSP 2007 SP1 – EV Bug report
In the Open Standard
Nader K. RadMember for 19 years 9 months
- Created
- 0
- 3
0
I have one task, with 1 assigned work resource (more than 100% unit). My only cost is resource per use cost.
Now, I have my baseline saved, and my task %complete is more than 0%. here is my resource sheet:
Resource information:
BCWP: 8350$
BCWS: 100$
ACWP: 100$
Cost: 100$
Task information:
BCWP: 100$
BCWS: 100$
ACWP: 100$
Cost: 100$
As you know, this resource BCWP should be 100$, but IT IS NOT!!!
This problem would not occure, if assignment unit is 100% or resource per use cost is 0$ (other costs would not make problems).
:(
Now, I have my baseline saved, and my task %complete is more than 0%. here is my resource sheet:
Resource information:
BCWP: 8350$
BCWS: 100$
ACWP: 100$
Cost: 100$
Task information:
BCWP: 100$
BCWS: 100$
ACWP: 100$
Cost: 100$
As you know, this resource BCWP should be 100$, but IT IS NOT!!!
This problem would not occure, if assignment unit is 100% or resource per use cost is 0$ (other costs would not make problems).
:(
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?