Skip to content

Automatic completion

Assaf FMember for 18 years 9 months
Created
1
2
0
Hi,
I have a milestone connected to an activity. That activity has been marked as complete (100%). How can I automatically turn the milestone to 100% also?

Thanks,
Assaf.

1 reply

Oldest first
  1. 0
    Darren Kosa ·
    Hi Assaf,

    The short answer is no, there isn’t an automated completion function for MS Project.

    As a work around you can group by the finish date and then change the relevant % Complete fields to 100%.

    The only other course of action is to go down the VBA route, but that’s beyond my capability unfortunately.

    Regards,

    Darren

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?