Calendar issues & incorrect calculation of completion

Nitin NaikMember for 21 years 8 months
Created
4
2
0
Hi

Further to my query, I have got the file which is having the problem of incorrect calculation.

The problem is calendar can only accept 10 non working days. Once you enter the 11th day it moves by 4 extra days showing the incorrect contract period.

Alex can you please send me your email address again to send the file.

I would like to send the file to any other person who can help me to resolve this issue.

Highly appreciate your help

Nitin

4 replies

Oldest first
  1. 0
    Charleston-Joseph Orbe ·
    Hello Nitin,

    I’ll try to unravel the mystery of your file.

    Is it possible to send attachment in Private Message? If yes, then PM me with the attach file.

    Otherwise you can sent it to my email address. I’ll PM you my email address in the event it will be confirm that no attachment in Private Message.

    Cheers,

    charlie
  2. 0
    Ker Song Sim ·
    Hi, I can try to help too, if you would PM me with attachment or indicate your email address in the PM.
  3. 0
    Charleston-Joseph Orbe ·
    Hi Nitin,

    I got the file that you send to my email (keep my email a secret).

    It may take a while for me to unravel the mystery of your file due to some pressing work to do and also...

    IT IS VALENTINE DAY TOMORROW, 14 February,

    I wish everyone in PP HAPPY Valentine Day.

    Cheers

    Charlie
  4. 0
    Charleston-Joseph Orbe ·
    Hello Nitin,

    What version of MSP was the file made in the first place. Im using MSP2002. When I open the file, there was a message of scheduling conflict of activity 575.

    Regards,

    Charlie

Log in or join to reply