Planned % Complete Macro
In the Open Standard
Karen PenderMember for 18 years 7 months
- Created
- 5
- 2
0
Hi,
I have been using a macro to calculate Planned % Complete when tracking my progress but for some reason it doesnt seem to be working anymore. The Planned % Complete Column isn’t changing once I change progress lines or run the macro.
I would be grateful if anyone has any ideas what could be wrong?
I have been using a macro to calculate Planned % Complete when tracking my progress but for some reason it doesnt seem to be working anymore. The Planned % Complete Column isn’t changing once I change progress lines or run the macro.
I would be grateful if anyone has any ideas what could be wrong?
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?