Macro to set the Free Float to 0

Andrew OwensonMember for 18 years 4 months
Created
7
3
0

Guys

 

I need a macro to set the Free Float to 0. Any takers?

 

Thanks in advance

 

Andrew

7 replies

Oldest first
  1. 0
    Rafael Davila ·

    For years people have been

    For years people have been asking for Microsoft to provide Zero Free Float Constraint instead of their implementation of Zero Total Float Constraint for ALAP (as late as possible).

    Remember such macro shall be applied to individual activities because if applied to all it will have the same effect of the Zero Total Float Constraint.

    Wish you good luck in your search for such macro. In theory a simple computation.

    Free Float (FF) = ES of next earliest successor - EF of activity

    I believe both are useful, unfortunately it is not what you need but what the software gives you. The software developer will tell you they know how to plan and you do not. That if you do not do it their way then you are wrong as they are the owners of absolute truth and that for your good they will not implement such functionality.

    Zero TT and Zero FF

    At times I miss SureTrak a low cost software that provided for both constraint options plus the expected finish constraint useful for long lead procurement activities. Also miss the WBS Activity Type and the Topic Activity Type. There is no such thing as a software with all the bells and wissels and we must learn to live with such reality.

    SureTrak Constraints

  2. 0
    Andrew Owenson ·

    Rafael I understand your

    Rafael

    I understand your comments, but I am not giving up yet. I have worked out how to apply a macro to set a constraint Start No Earlier Than to each activity. I applied this formula to a date column [Early Start]+([Free Slack]/480). This should have given me the date I needed, but it does not take into account the calender for the project. I can also undo the macro so that the project returns to normal.

     

    Does anyone know how to incorporate the calendar reference to the formula so that MSP can work out a correct date.

     

    Regards

     

    Andrew

  3. 0
    Rafael Davila ·

    Andrew, I agree with you

    Andrew,

    I agree with you don't give up yet.

    Please take a look at the following formula and then the following screen movie that might give you some hints.

    FS Date Formula

    http://www.youtube.com/watch?v=U9xaQHOXXXI

    You can make your Paste Special to be applied to the whole column/all activities or to individual activities.

    For the undo macro you might need to temporarily copy-paste Date 1 into constraint date without special paste, then you will be able to remove the constraint.

    Best regards,

    Rafael

    P.S. - GIGO

  4. 0
    Rafael Davila ·

    Keep in mind some software

    Keep in mind some software after resource leveling will yield wrong float values.

    In the following example a four activities schedule, none linked by logic but all requiring one unit of resource A of which only one unit is available MS Project yields wrong values of float after resource leveling.

    I am not sure what you are tring to obtain will be valid under resource leveling in MS Project.

    Resource leveled floats

    Spider Project is displaying the correct values, all zero.

    Even Primavera SureTrak displays wrong FF values after resource leveling as shown in the following figure.

    SureTrak FF wrong after RL

    I am not sure but after years of warnings about it I believe P6 developers finally got it, so they are trainable but Microsoft people are very stubborn.

    Well I must recognize they got to be very brave to display such horrendous errors for years and do nothing. Here we call such people "cara de lata" Spanish for "tin face". I wonder how much money has been lost to such negligent display of erroneous values without any warning to the user.

  5. 0
    Bo Johnsen ·

    Andrew, You could probably

    Andrew,

    You could probably use the ProjDateDiff-function which takes the calendar of your choice into consideration. Date1=Early Start, Date2=Early Start+Free Slack, calendar="your calendar" (from MSP Help: ...the calendar to use when calculating the duration. If calendar is not specified, the default for the current resource is the resource calendar, or for the current task, the task calendar (or the standard calendar if there is no task calendar)).

    Otherwise I can suggest to post your question on: http://social.technet.microsoft.com/Forums/en-US/projectprofessional2010general/threads where some people with really good knowledge of macros and VBA within MS Project are normally very helpful to answer your questions. Probably the biggest forum for discussion of MS Project. Free, but requires a Windows Live ID.

    Regards,

    Bo

     

  6. 0
    Bo Johnsen ·

    Andrew, Just forget my

    Andrew,

    Just forget my posting below. Can see you have already posted your question on the suggested site...

    Bo

  7. 0
    Rafael Davila ·

    Because MS Project yields

    Because MS Project yields wrong float calculations after resource leveling it might be impossible to create a macro to set free slack to zero under resource leveling using the computed values of float.

    In the following example after the resource leveling is run MS Project yields wrong float values and by setting wrong float values to zero the schedule is delayed and becomes unleveled, then in order to level it you must run again the resource leveling and then after setting your wrong values of float equal to zero you end up delaying once more time the whole schedule. MS Project ridiculous float computations might yield ridiculous results.

    http://www.youtube.com/watch?v=ciTfD1Tgw9E

    Is common sense, MS Project calculations for float under resource leveling are wrong therefore any attempt to set zero float after resource leveling using wrong float values will yield wrong results.

    As Lady Gigo sings, Garbage In - Garbage Out

    Primavera SureTrak same as MS Project yields wrong float values after resource leveling but they have a zero free float constraint with their option for ALAP. Therefor it is not impossible to get to it, surely not by means of their float computation.

    But beware that SureTrak wrong computations of float after resource leveling yields weird implementation of the Zero Free Float constraint, is kind of unpredictable same as P3.

    http://www.youtube.com/watch?v=AQPaM5Vxvpw

    Why do you think early users of P3 could not figure out the logic in their schedules if from the very beginning float values were wrong?

    I would not be surprised at all if latest versions of Pertmaster still display wrong values of float after resource leveling.