Planned % complete column

Christopher PaulrajMember for 17 years 8 months
Created
6
5
0
Can you please tell me how to get a Planned % complete column? Basically i wanted to have a progress programme showing % complete column, planned % complete column and planned and actual start dates?

6 replies

Oldest first
  1. 0
    Darren Kosa ·
    Christopher,

    This thread should suit your needs. Look at post #2 from Niek Zonneveld.

    Display Baseline Percent complete in MS Project

    By the way you need to set a baseline for it to work. ;o)

    Regards,

    Darren
  2. 0
    Christopher Paulraj ·
    Thanks Darren,

    The formual perfectly works, but it doesn’t calaculate for summary bars. is there any solutions to calculate the baseline % complete for summary bars?

    Rgds
    Chris
  3. 0
    Darren Kosa ·
    Chris,

    Whichever field you’ve used to show Planned % Complete, should also have ‘calculation for task and group summary rows’ options. Check the ‘use formula’ radio button and it should then roll up to summary levels.

    (Tools > Customize > Fields)

    Regards,

    Darren
  4. 0
    Se de Leon ·
    There’s another way to do this.

    Saving a separate file of your baseline project, and name it as "as planned" file. Use the Tools Tracking as complete through, then assign a date. After MPP calculates the % complete, copy paste this field to your baseline or current project as a text field. This is similar to P3, the only difference is you have to cut and paste the calculated as planned %, not assign the "as planned" schedule as a target schedule.

    what darren has explained is perfect if you really want a dynamic way of showing the as planned %. If you have not get the hung of the complicated formula, you may use the above as an alternative way to show as planned %.

    Cheers,
  5. 0
    Christopher Paulraj ·
    Thanks

    Is there any way to calculate potential days delay or Slip?

    Rgds
    Chris
  6. 0
    Se de Leon ·
    As long as you have a proper CPM in your schedule, you can always calculate delays in MPP.

    Step 1: Update completely and accurately your project
    Step 2: Use Tools Tracking Update Project, then click Reschedule uncompleted work to start, then assign a date.
    Step 3: Review your updated Critical Path
    Step 4: if you can do it, mitigate delays, if not, voila, you have your updated completion date.

    I hope this helps.

Log in or join to reply